Date of work:2019 - 2021 Repair of more than one hundred subsea concrete piles by adding new fiber covers and epoxy mortar pumped from the dock and structural elements.
Installation of Dolos - Cristobal's Breakwaters
Date of work:2021-2022 Transportation and installation of 500 8-ton concrete dolos on the Cristobal breakwater.
Re Enforcement Of The Pier Abutment Structure At Melones Oil Terminal